Logo Logo Logo Logo
  • CONTACT
  • CLIENTS
  • TESTIMONIALS
  • Projects
    • Completed Projects Archive
    • Current Projects
      • Ongoing Maintenance Projects
      • Current Projects 2020
    • Completed Projects
      • Completed projects 2013
      • Completed Projects 2017
      • Completed Projects 2016
      • Completed Projects 2015
      • Completed Projects 2014
      • Completed Projects 2012
      • Completed Projects 2018
      • Completed Projects 2019
  • HOME
  • ABOUT US
  • CONTACT
  • CLIENTS
  • TESTIMONIALS
  • Projects
    • Completed Projects Archive
    • Current Projects
      • Ongoing Maintenance Projects
      • Current Projects 2020
    • Completed Projects
      • Completed projects 2013
      • Completed Projects 2017
      • Completed Projects 2016
      • Completed Projects 2015
      • Completed Projects 2014
      • Completed Projects 2012
      • Completed Projects 2018
      • Completed Projects 2019
  • HOME
  • ABOUT US
21 Jul

Zurich

By Mechanical Engineering Dublin | Current Projects 2020

G&J Engineering limited were awarded the project of replacing existing 6no. floor mounted Gas fired boilers.

This project was completed within the specified timeframe with minimal disruption to the building staff.

The scope of works included Isolation of existing services, Removal & disposal of existing boilers and flues, Installation of 6no. 110 kw high efficiency stainless steel heat exchanger boilers, Cascade, Circulating pumps, Flues, alterations to existing distribution pipework, Insulation, labelling, testing & commissioning.

0
0
21 Jul

United Drug

By Mechanical Engineering Dublin | Current Projects 2020

G&J Engineering limited were awarded the project of replacing existing 2no. floor mounted Gas fired boilers.

This project was completed within the specified timeframe with minimal disruption to the building staff. These essential works required a contract crane lift to remove the existing Gas boilers & to position the new Gas boilers within a roof plantroom.

The scope of works included Isolation of existing services, Removal & disposal of existing boilers and flues, Removal & disposal of existing 100mm Gas main pipework, Installation of 2no. 400kw high efficiency Rendamax boilers, Circulating pumps, Flues, Spirocross Magnetic strainer, 100mm roof Gas main replacement, alterations to existing distribution pipework, Insulation, labelling, testing & commissioning.

0
0
21 Jul

Bon Secour Hospital

By Mechanical Engineering Dublin | Current Projects 2020

G&J Engineering limited were awarded the project Diagnostic hub

The scope of works included replacing existing supply & extract ductwork, removal of redundant chilled water pipework, relocation of Air conditioning units this was to facilitate the installation of new roofing insulation and membrane.

This project was completed within the specified timeframe with minimal disruption to the building services.

Engineer: Homan & O’Brien

0
0
21 Jul

Bon Secour Hospital

By Mechanical Engineering Dublin | Current Projects 2020

G&J Engineering limited were awarded the project St Mary’s ward

The scope of works included replacing existing HWS, CWS, MWS, HWSR distribution pipework, Installation of radiant panels, LPHW distribution pipework, Controls, insulation, labelling, testing & Commissioning.

This project was completed within the specified timeframe with minimal disruption to the building services.

Engineer: Homan & O’Brien

0
0
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • 23
  • 24
  • 25
  • 26
  • 27
  • 28
  • 29
  • 30